PRACTICAL CHALLENGES OF ORGANISING AND CONDUCTING INTERNATIONAL COMPETITIVE BIDDING (ICB) IN PROJECT IMPLEMENTATION UNITS: INSTITUTIONAL CAUSES OF DELAYS

Authors

  • Ergashev Radjabjon Rustamovich Ministry of Agriculture of the Republic of Uzbekistan, Tashkent. Author

Keywords:

International Competitive Bidding, ICB, Project Implementation Unit, procurement delays, institutional capacity, bid evaluation, procurement planning, international financing, accountability, project management.

Abstract

 This article examines the practical challenges of organising and conducting International Competitive Bidding (ICB) in Project Implementation Units (PIUs), with particular emphasis on institutional factors that delay procurement and project implementation. It analyses the effects of inadequate procurement planning, limited staff capacity, complex approval procedures, deficiencies in bidding documentation, lengthy bid evaluation, coordination problems, and weak accountability mechanisms. Evidence from World Bank project evaluations indicates that procurement delays are frequently associated with poor-quality bidding documents, difficulties in applying evaluation criteria, insufficient procurement expertise, and delayed internal decision-making. The article proposes institutional measures to improve procurement efficiency, including early procurement planning, professionalisation of PIU staff, clearer delegation of authority, standardised documentation, risk-based review, and systematic monitoring of procurement timelines.

References

1.Independent Evaluation Group, World Bank Group. Making Procurement Work Better: Chapter 2 — Improving Procurement Efficiency. World Bank Group. Available at: https://ieg.worldbankgroup.org/evaluations/making-procurement-work-better/chapter-2-improving-procurement-efficiency

2.World Bank. Procurement Regulations for IPF Borrowers. World Bank Procurement Framework. Applicable edition to be determined according to the project’s financing and procurement arrangements. Available at: https://www.worldbank.org/ext/en/what-we-do/project-procurement/framework

3.Asian Development Bank. Strategic Procurement Planning. Guidance Note, December 2021. Available at: https://www.adb.org/documents/procurement-planning

4.World Bank. Uzbekistan: Project Appraisal Document. Procurement Capacity Assessment and procurement-risk mitigation measures. Available at: https://documents.worldbank.org/curated/en/635091480129220617/pdf/Uzbek-PAD-11042016.pdf

5.World Bank. Project Appraisal Document: Procurement Risk Assessment and Mitigation Measures. Discussion of procurement capacity, bidding documentation, language-related constraints, and implementation risks. Available at: https://documents1.worldbank.org/curated/en/944911468023332501/pdf/PAD6110PAD0P14010Box385454B00OUO090.pdf

6.Asian Development Bank. Procurement Policy: Goods, Works, Nonconsulting and Consulting Services. October 2017, applicable to projects as specified in the policy and subsequent procurement framework updates. Available at: https://www.adb.org/documents/adb-procurement-policy

7.Asian Development Bank. Project Procurement Framework. Principles of economy, efficiency, fairness, transparency, quality, and value for money. Available at: https://www.adb.org/business/project-procurement/framework

Downloads

Published

2026-10-15